Once drawings are approved, the build is the bit that decides whether you get the home you imagined or a frustrating compromise. We deliver projects on a single contract — design, drawings, approvals and construction — so the team that drew it is the team that builds it. In Mousehole, that work is shaped by the place itself — Mousehole is a famously photogenic fishing village south of Newlyn, almost entirely within the Conservation Area and AONB, with a tiny harbour and dense lanes of granite cottages, with a building stock that leans toward granite fishing cottages and Victorian villas above the village.
- Conservation Area
- Cornwall AONB
- Coastal exposure zone
Local context
Why Mousehole is its own job.
Almost the entire village is within both the Conservation Area and AONB; new openings, dormers, render colours and roof materials all attract close scrutiny. Paul parish operates with strong policy resistance to second-home use. For full build package specifically, parts of Mousehole sit within a designated Conservation Area, which means materials, fenestration and roof pitches all need to read sympathetically with the existing streetscape; the surrounding landscape falls inside the Cornwall Area of Outstanding Natural Beauty, so massing, height and landscape impact carry extra weight in any planning decision; coastal salt-laden air around Mousehole drives detailing choices — fixings, render systems and timber treatments all need to be specified for exposure. That's why we treat every Mousehole project as a TR19-area job first — not a generic Cornwall job with a postcode bolted on.
Planning note
Build delivery doesn't need planning, but planning conditions often dictate site setup, materials and working hours — we read every condition and build the programme around them.
What we focus on
Full Build considerations specific to Mousehole.
01
Cornish trades are a tight community; using contractors who've worked together before saves weeks on programme and arguments on site.
02
Single-contract delivery removes the gap between architect's intent and builder's interpretation — fewer change orders, less variation cost.
03
Material lead times to Cornwall are longer than the M5 corridor; sequencing orders early protects the build programme.
Our process
How a Mousehole full build package project runs.
Step 1
Pre-construction
Programme, procurement, contractor briefing and site setup.
Step 2
Substructure
Foundations, drainage, ground beams — the unglamorous bit that decides everything later.
Step 3
Superstructure
Frame, roof, glazing — getting the building watertight.
Step 4
First and second fix
Services, plaster, joinery, kitchens and bathrooms.
Step 5
Snag and handover
Final inspection, building control sign-off, handover pack and aftercare.
Full builds run from twelve weeks for small extensions to eighteen months for new build family homes.
FAQs
Mousehole Full Build — common questions.
- What guarantees and aftercare do you offer?
- Standard twelve-month defects period, plus product and workmanship warranties on relevant elements. We're a Cornish business — you'll still find us in the same studio in five years' time. In Mousehole specifically, we'd start by checking the Conservation Area boundary before committing to a direction.
- Fixed price or open book?
- Both. Fixed price suits well-defined projects with clear specs; open book suits renovations and listed work where the unknowns only reveal themselves once you start opening things up. We'll recommend the right route.
- Do you handle the whole project from drawing to finish?
- Yes — that's the model. One contract from feasibility to handover, with design, regs and build all under our roof. No coordination gap between designer and contractor.
- Are you insured?
- Public liability, employer's liability and contractor's all-risks cover are in place for every project, with certificates available before contract signing.
Other services in Mousehole
Nearby places we cover