How long does a Cornwall project really take, from first call to starting on site?
The statutory determination period for a householder application is eight weeks, and thirteen for major schemes. That number is the smallest part of the answer. The realistic programme is set by the design stage before submission, validation, and the conditions that have to be discharged afterwards.
Free · No obligation
Ask us about your project
A free first conversation — no obligation, no sales calls.
Frequently asked
Straight answers.
- Can I start work as soon as permission is granted?
- Only if there are no pre-commencement conditions. Many Cornish consents carry conditions on materials, drainage or ecology that must be discharged first, and starting before that can render the permission unimplemented.
- How long is planning permission valid?
- Standard consents are typically valid for three years from the decision, within which a material start must be made. Renewal is not automatic and policy may have changed by then.
- Does building regulations run alongside planning?
- It can, and running the building regulations package in parallel with the tail end of the planning stage is the most common way to save real time on a project.
- What is the fastest realistic route to starting on site?
- A permitted development scheme with a lawful development certificate and a full plans building regulations application, run in parallel. Where the design fits, it is substantially quicker than a planning application.
Working to a deadline?
Tell us when you want to be on site and we will map the stages backwards from it.